contractor PSEG has identified 10 potential routes for transmission lines regional electrical grid operator PJM says are ...
Public Service Enterprise Group (PSEG) would like to build a new transmission line spanning a swath of Maryland, deeming it a ...
PJM Interconnection and Pennsylvania Governor Josh Shapiro have settled a lawsuit over PJM’s capacity market pricing, ...
The 359 MW Wagner Unit 3 was completed in 1966 as a coal-fired unit that Talen converted to run on fuel oil at the end of ...
PJM Interconnection — the regional power grid operator — is predicting a "significant growth in electricity demand " over the next 20 years. PJM estimates the peak summer demand for its 13-state ...
As one energy solution, the Maryland Piedmont Reliability Project, a proposed 70-mile transmission line, that would run through Baltimore, Carroll and Frederick Counties, was proposed by both PJM ...