Dominion Energy said Coastal Virginia Offshore Wind project is 50% complete and remains on track for on-time completion at ...
The regulated utility entered supplier contracts in 2021 that allowed it to skirt surging inflation that drove US sector ...
Dominion Energy has stated that the 2.6GW Coastal Virginia Offshore Wind (CVOW) project is now approximately 50% complete and ...
Callsen’s bill also raises to 600 MW, from 200 MW currently, the target for solar on previously developed sites. It also ...
The utility overcame numerous challenges while rebuilding its Mt. Storm to Valley line in extreme mountainous terrain.
President Donald Trump's order pausing efforts to plant wind turbines off U.S. coasts won’t affect Dominion's $9 billion ...
Despite President’s order that freezes most sector activity, utility is 'confident CVOW will be completed on-time, and that ...
"Rising electric bills are forcing Virginians to choose between keeping the lights on and putting food on the table," a ...
Activists and politicians spoke out in support of protecting the Virginia Clean Economy Act (VCEA) at an event organized by the Sierra Club Virginia Chapter on Monday morning.
Dominion Energy is still moving full speed ahead on the construction of the Coastal Virginia Offshore Wind (CVOW) project, ...
Dominion Energy is expanding its Possum Point Power Station in Prince William County, Virginia, to meet the growing power ...
Richmond, Virginia-based Dominion Energy, Inc. (D) engages in regulated and non-regulated electricity distribution, ...